GRACE Monthly Report from February 2015 is available
The GRACE Science Data System Monthly Report from February 2015 is available now. For Details see:
SDS Monthly Report February 2015.
Note: Highlights this month:
* A 2-days orbit repeat cycle caused problems to calculate nominal Level-2 products for February 2015. This problem has and will also affect the January and March 2015 solutions. The SDS has worked on solution stabilization strategies resulting in the products as described in the following.
* CSR has generated and delivered following RL05 Level-2 products for February 2015 (Please refer to the corresponding notes on the CSR website and to the CSR L2 Release Notes):
* A standard 60x60 solution where more aggressive than normal post-processing may be required.
* Additionally, a deviant 60x30 product for experimental use is provided too.
* No 96x96 solution will be generated and delivered.
* GFZ has generated and delivered following RL05a Level-2 products for February 2015 (see also GFZ L2 Release Notes):
* A regularized 90x90 solution where more aggressive than normal post-processing may be required.
* Additionally, a deviant 90x30 product for experimental use is provided too.
* JPL has generated and delivered following RL05.1 Level-2 products for February 2015 (see also JPL L2 Release Notes):
A standard 60x60 solution where more aggressive than normal post-processing may be required.
* The next GRACE Science Team Meeting is scheduled for September 21-23, 2015 in Austin. Further information will follow on the GSTM website at CSR at http://www.csr.utexas.edu/grace/GSTM/
|
|
 |
|